Week Two Midweek Report

The garage was formed and poured on Monday, forms came off on Tuesday, outside sprayed on Wednesday:








One of the pleasures has been almost daily visitors to the site:







Now on Wednesday the basement plumbing work started. Bruce did some backfilling so the basement is approachable and Slick and his crew put down the drain lines and put in the well water line:








Next on the docket.....septic tank and field installation.